Frozen state funds, uninstalled equipment and stranded projects totaling about Br100 billion identified in a joint inspection prosecutors and SCC Vitebsk region. These data were presented during a joint session of the two agencies on the effectiveness of plans to modernize and use of equipment.
On behalf of the President, given at a meeting on the results of the real economy in 2014, the SCC together with the Prosecutor's Office conducted an inspection of the results of modernization in the organization of industry and construction. "Control and analytical activities have shown that individual enterprises modernization was carried out, but no result and not calculated in the near future. The acquired equipment remains unknown for a long time, surface-developed business plans fail. Growing investment costs and the expected economic effect is not achieved. Frozen public funds are not set in the period of the equipment and the delay in the implementation of investment projects totaling about Br100 billion identified in enterprises of different departmental subordination ", – noted Deputy Chairman of the State Control Committee Vitebsk region Julia Avhukova.
The most important parameters of the competitiveness of products can not be achieved, which contributes to higher prices, loss of markets. For example, the export of construction services in the region in 2014 amounted to only 23.8% of the jobs and exports of construction materials decreased by 28.5% compared with 2013 year. And this despite the fact that modernized the two largest construction companies – Vitebsk DSC and building trust №16 Novopolotsk. None of the projects to be completed. On the CMT №16 for three years is not used equipment purchased for investment projects. Not running line automatic feeding of concrete, as a result of automatic cost Br5 idle billion, and the company incurs additional costs for concrete transport shuttle service. Such examples of the construction sector was made at a meeting of about a dozen. "These facts indicate a lack of work of the Ministry of Architecture and Construction, Executive Committee to monitor the timely implementation of measures to modernize and rational use of resources at the enterprises", – Yulia Avhukova.
In a pinch, control needs and the work of industrial enterprises. For irrational use of the innovation fund, missed deadlines modernization and implementation of major investment projects were criticized of "Hero", "Plant automatic control devices," PMC "Dawn", JSC "Polotsk-bargaining", JSC "BelVitunifarm." Also found evidence of inefficient use of health care facilities funds to purchase equipment. One of the most sensitive issues is the situation with the modernization in the agricultural sector. Construction of dairy farms in some areas being extremely slow pace, there is evidence of delivery of defective equipment. But instead of issuing claims agricultural companies to invest in the purchase of a new one.
Business leaders are taking inadequate measures of safety equipment, allow the facts of mismanagement, said head of the department for supervision over the implementation of laws and legality of legal acts of the Prosecutor's Office of Vitebsk region Irina Yanukovych. Prosecutors on an ongoing basis to review and monitor the situation and fix both primary and repeated violations. During these audits were made ten submissions and five precepts. "Often only after the intervention of the prosecutor company management takes measures to ensure proper storage of purchased equipment," – added Irina Yanukovych.
The meeting was attended by the First Deputy Chairman of the Executive Committee Gennady crest, representatives of the Ministry of Industry and the Ministry of Architecture and Construction, chairmen and executive committees of a number of business leaders. According to the results taken binding decisions to resolve the problems identified.